(45)-VALUATION BASIS OF FIXED ASSETS

Valuation Basis of Fixed Assets

The following valuation basis should be used for properties that are not impaired.
  • Specialized properties should be valued on the basis of depreciated replacement cost.
    Specialized properties are those which, due to their specialized nature, are rarely, if ever, sold on the open market for single occupation for a continuation of their existing use, except as part of a sale of the business in occupation.

Example; oil refineries, chemical works, power stations, or schools, colleges and universities where there is no competing market demand from other organizations using these types of property in the locality.

  • Non specialized properties should be value on the basis of existing use value.
  • Properties surplus to an entities requirements should be value on the basis of open market value.

Where there is an indication of impairment, an impairment review should be carried out in accordance with Financial Reporting Standards. The asset should be recorded at the lower of revalued amount and recoverable amount.

Tangible fixed assets other than properties should be valued using market value or, if not obtainable, depreciated replacement cost.

Monday, December 7, 2009

(44)-FINANCIAL REPORTING STANDARDS RULES FOR FIXED ASSET REVALUATION

Financial Reporting Standards Rules for Fixed Asset Revaluation

An entity may adopt a policy of revaluation tangible fixed assets. Where this policy is adopted it must be applied consistently to all assets of the same class.

A class of fixed assets is a category of tangible fixed assets having a similar nature function of use in the business of an entity.

Where an asset is revalued its carrying amount should be its current value as at the balance sheet date current value being the lower of replacement cost and recoverable amount.
To achieve he above, the standard stats that a full valuation should be carried out at least every five years with an interim valuation in year3. If it is likely that there has been a material change in value, interim valuation in year 1, 2 and 4 should also be carried out.


A full valuation should be conducted by either a qualified external value or a qualified internal value, provided that the valuation has been subject to review by a qualified external assessor. An interim valuation may be carried out by either an external or internal assessor.

For certain types of assets, there may be an active second hand market for the asset or appropriate indices may exist, so that the directors can establish the assets value with reasonable reliability and therefore avoid the need to use the services of a qualified assessor.

Sunday, December 6, 2009

(43)-TANGIBLE FIXED ASSETS

Tangible Fixed Assets

A tangible fixed asset should initial measured at cost.

Cost is purchase price and any cost directly attributable to bringing the asset into working condition for its intended use.
For example of directly attributable costs are;

  • Acquisition costs such as stamp duty
  • Cost of site preparation and clearance
  • Initial delivery and handling costs
  • Installing costs
  • Professional fees like legal fees
  • The estimated cost of dismantling and removing the asset and restoring the site
    Any abnormal costs, such as those arising from design error, industrial disputes or idle capacity are not directly attributable costs and therefore should not be capitalized as part of the cost of the asset.

Finance costs

The capitalization of finance costs, including interest, is optional. However if an entity does capitalize finance costs they must do so consistently.

All finance costs that are directly attributable to the construction of a tangible fixed asset should be capitalized as part of the cost of the asset.

Directly attributable finance costs are those that would have been avoided if there had been no expenditure on the asset.

If Finance costs are capitalized, capitalization should start when,

  • Finance costs are being incurred
  • Expenditure on the asset is being incurred
  • Activities necessary to get the asset ready for use are in progress

Capitalization of finance costs should cease when the asset is ready for use.

Subsequent expenditure

Subsequent expenditure on a tangible fixed asset should only be capitalized in the following three circumstances.

  1. It enhances the economic benefits over and above those previously estimated. An example might be modifications made to a piece of machinery that increases its capacity or useful life.
  2. A component of an asset that has been treated separately for depreciation purposes has been restored or replaced.
  3. It relates to a major inspection or overhaul that restores economic benefits that have been consumed and reflected in the depreciation charge.

Saturday, December 5, 2009

(42)-DISCLOSURES FOR FIXED ASSETS IN FINANCIAL STATEMENTS

Disclosures for Fixed Assets in Financial Statements

Notes to the accounts must show, for each class of fixed assets, an analysis of the movements on both cost and depreciation provisions.

Where any fixed assets of a company other than listed investments are included in the accounts at an alternative accounting valuation, the following information must also be given.
  • The years so far as they are known to the directors in which the assets were severally valued and the several values.
  • In the case of assets that have been valued during the financial period, the names of the persons who valued them or particulars of their qualification for doing so and whichever is stated the bases if valuation used by them.

A note to the accounts must classify land and buildings under the headings of;

  • Freehold property
  • Leasehold property,
  • Long leaseholds in which the unexpired term of the lease at the balance sheet date is not less than 50 years
  • Short leaseholds which are all leaseholds other than long leaseholds.

Friday, December 4, 2009

(41)-REVALUATION RESERVES FOR FIXED ASSETS

Revaluation Reserves for Fixed Assets

Where the value of any fixed asset is determined by using the alternative accounting rules the amount of profit or loss arising must be credited or as the case may be debited to a separate reserve, the revaluation reserve. The calculation of the relevant amounts should be based on the written down values of the assets prior to revaluation.

The revaluation reserve must be reduced to the extent that the amounts standing to the credit of the reserves are, in the opinion of the directors of the company, no longer necessary for the purpose of the accounting policies adopted by the company.

However, an amount may only be transferred from the reserve to the profit and loss account if either,
  • The amount in question was previously charged to that account.
  • It represents realized profit.

The only other transfer possible from the revaluation reserve is on capitalization, that is, when a bonus issue is made.

The amount of a revaluation reserve must be shown under a separate sub heading on the balance sheet. However the reserve need not necessarily be called a “revaluation reserve”.

Wednesday, December 2, 2009

(40)-VALUATION OF FIXED ASSETS

Valuation of Fixed Assets

Where an asset is purchased, its cost is simply the purchase price plus any expenses incidental to its acquisition.

Where an asset is produced by a company for its own use, its production cost must include the cost of row materials, consumables and other attribute direct costs such as labour cost. Production cost may additionally include a reasonable proportion of indirect costs, together with the interest on any capital borrowed to finance production of the asset.

The cost of any fixed asset having a limited economic life, whether purchase price or production cost, must reduced by provisions for depreciation calculated to write off the cost, less any residual value, systematically over the period of the assets useful life. This very general requirement is supplemented by the more detailed provisions of financial reporting standards.

Provision for a permanent reducing in value of a fixed asset must be made in the profit and loss account and the asset should be disclosed at the reduced amount in the balance sheet. Any such provision should be disclosed on the face of the profit and loss account or by way of note. Where a provision becomes no longer necessary, because the conditions giving rise to it have altered, it should be written back, and again disclosed should be made.

Tuesday, December 1, 2009

(39)-LEDGER ACCOUNTING ENTRIES FOR THE FIXED ASSET DISPOSALS

Ledger Accounting entries for the Fixed Asset Disposals

A profit on disposal is an item of other income in the profit and loss account, and a loss on disposal is an item of expense in the profit and loss account.

It is customary in ledger accounting to record the disposal of fixed assets in a disposal of fixed asset account. The profit or loss on disposal is the difference between,
  • The sale price of the asset, and
  • The net book value of the asset at the time of sale.

The relevant items which must appear in the disposal of fixed assets account are therefore,

  • The value of the asset, at cost or revalued amount.
  • The accumulated depreciation up to the date of sale.
  • The sale price of the asset.

For the disposal of fixed assets; ledger accounting entries are as follows,

  1. Transfer the cost of fixed asset, to disposal of fixed asset account.
    Disposal of fixed asset account --Debit
    Fixed asset account --Credit
  2. Transfer the accumulated depreciation on the asset as at the date of sale.
    Provision for depreciation account --Debit
    Disposal of fixed asset account --Credit
  3. Transfer the sale price of the asset. The sale is therefore not recorded in a sales account, but in the disposal of fixed asset account itself.
    Debtor account or cash book --Debit
    Disposal of fixed asset account --Credit
  4. The balance on the disposal account is the profit or loss on disposal and the corresponding double entry is recorded in the profit and loss account,
    • If loss
    Profit and loss account --Debit
    Disposal of fixed asset account --Credit
    • If profit
    Disposal of fixed account --Debit
    Profit and loss account --Credit